The Sope Creek parking lot of the Chattahoochee River National Recreation Area will be closed for pavement repairs beginning July 27, 2009 through Aug. 21, 2009. The large sinkhole in the parking lot will be repaired in addition to seal coating and restriping the lot. Closures are scheduled for weekdays which will allow for full use of the park on the weekends. Below is the schedule of work and closed periods.
Repair Sink Hole - Lot Closed
July 27-29
Saw Cut Asphalt Repair Areas
July 30-31
Remove Asphalt in Repair Area
August 3
Replace Curb and Gutter
August 3-5
Asphalt Patch in Repair Areas
August 6-7
Crack Seal - Lot Closed
August 10
Seal Coat - Lot Closed
August 11-12
Re-Stripe Areas - Lot Closed
August 14
Final Clean-up
August 17
Punchlist
August 18-19
Project Closeout
August 20-21
Source: U.S. Department of the Interior, National Park Service