The Sope Creek parking lot of the Chattahoochee River National Recreation Area will be closed for pavement repairs beginning July 27, 2009 through Aug. 21, 2009. The large sinkhole in the parking lot will be repaired in addition to seal coating and restriping the lot. Closures are scheduled for weekdays which will allow for full use of the park on the weekends. Below is the schedule of work and closed periods.

Repair Sink Hole - Lot Closed

July 27-29

Saw Cut Asphalt Repair Areas

July 30-31

Remove Asphalt in Repair Area

August 3

Replace Curb and Gutter

August 3-5

Asphalt Patch in Repair Areas

August 6-7

Crack Seal - Lot Closed

August 10

Seal Coat - Lot Closed

August 11-12

Re-Stripe Areas - Lot Closed

August 14

Final Clean-up

August 17

Punchlist

August 18-19

Project Closeout

August 20-21