Hanford Waste Treatment Plant Continues Progress Toward Commissioning

Webp 7edited

Hanford Waste Treatment Plant Continues Progress Toward Commissioning

The following press release was published by the U.S. Dept. of Energy, Office of Environmental Management on July 21, 2020. It is reproduced in full below.

RICHLAND, Wash. - Workers at Hanford ’s Waste Treatment and Immobilization Plant (WTP) recently completed startup testing on another significant plant system, the utility building that provides power to the plant’s Effluent Management Facility, pictured above. The system is one of many going through commissioning prior to starting low-activity tank waste treatment through the Direct-Feed Low-Activity Waste (DFLAW) approach. This development at WTP supports one of EM's 2020 priorities: complete DFLAW construction turn-over to commissioning.

Source: U.S. Dept. of Energy, Office of Environmental Management