Hanford Effluent Treatment Facility Puts Upgrades to the Test

237

Hanford Effluent Treatment Facility Puts Upgrades to the Test

After another year of extensive equipment upgrades, EM Office of River Protection (ORP) tank operations contractor Washington River Protection Solutions (WRPS) is conducting its fiscal 2022 processing campaign at the Hanford Site’s Effluent Treatment Facility (ETF) with a goal to process approximately 1 million gallons of wastewater over the next few months.

The facility removes radioactive and hazardous contaminants from wastewater generated by tank waste activities, groundwater projects, solid waste disposal facilities and other Hanford cleanup activities.

“The resumption of facility operations is important to the Hanford Site cleanup mission,” said Bibek Tamang, ORP program manager. “Enhancements to the facility will also be critical to the success of Hanford’s tank waste treatment mission.”

The ETF is one of several Hanford facilities being upgraded to support the Direct-Feed Low-Activity Waste (DFLAW) Program for treating tank waste by immobilizing it in a glass form. When fully operational, Hanford’s Waste Treatment and Immobilization Plant will be the primary generator of liquid waste to be treated by the ETF.

“The upgrades and additions of some new equipment will increase the Effluent Treatment Facility’s capability, efficiency and reliability to handle the increase in wastewater volume,” said Tamang. “When working at full capacity, the Waste Treatment and Immobilization Plant is expected to produce as much as 5.4 million gallons of effluent per year that will need to be treated at the Effluent Treatment Facility.”

Annual wastewater treatment totals in the past have varied as Hanford cleanup work has progressed. The ETF processed 3.2 million gallons of wastewater during its last campaign, which ended in February 2021, and between 1 million and 4 million gallons in each of the three previous years.

“We will be seeing longer and larger processing campaigns when tank waste treatment begins,” said Brandon McFerran, ETF manager for WRPS. “Testing the new equipment and components during this year’s processing campaign will give us lessons learned for the years ahead.”

Since beginning operations in 1995, the facility has processed more than 330 million gallons of contaminated wastewater to remove radioactive and chemical waste.

This is the third year of renovations and modernization of the nearly 30-year-old facility. Once this year’s wastewater treatment campaign is completed, ETF will undergo a final round of improvements to accommodate future DFLAW needs.